Question: Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V - - - U W 35 50 65

Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V - - - U W 35 50 65 V W,X 28 40 52 W Z 26 35 44 X Y 28 40 52 Y