Question: Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V U W 35 50 65 V W,X 28

Consider the following work breakdown structure:

Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V U W 35 50 65 V W,X 28 40 52 W 26 35 44 Y 28 40 52 Y Z 26 29 38 Z End 36 60 84 N X E Z What is the estimated expected (mean) time for project completion? Select one: a. 255 days b. 170 days C. 180 days d. 145 days e. 135 days