Question: Consider the following work breakdown structure: Duration Estimates (Days) Optimistic Most Likely Pessimistic Activity Start Precedes U.V W W.X > > End What is the

Consider the following work breakdown structure:

Consider the following work breakdown structure: Duration Estimates (Days) Optimistic Most Likely Pessimistic Activity Start Precedes U.V W W.X > > End What is the estimated slack time for activity W? 45 days 85 days 0 days 25 days 35 days