Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start B Precedes A, B, C D E End F. End

Consider the following work breakdown structure:
Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start B Precedes A, B, C D E End F. End End 38 90 85 19 91 62 50 99 100 25 100 65 D E F 62 108 115 31 115 68 What is the estimated standard deviation in the time for activity E? What is the estimated standard deviation in the time for activity E? Multiple Choice O 2 days 3 days O 4 days 16 days