Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B,C D 50 62 108 B 38 90

Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B,C D 50 62 108 B 38 90 85 19 E End F D 99 100 25 100 65 E End End 115 31 115 68 91 62 F What is the estimated slack time for activity A? 20 days 100 days O days 60 days 40 days