Question: Consider the following work breakdown structure: Finish Start Most Likely Pessimistic Node 5 0 6 0 7 0 4 1 5 4 5 8 3
Consider the following work breakdown structure: Finish Start Most Likely Pessimistic Node What is the estimated expected mean time for activity D A days B days c days D days E days