Question: 84 093 QUESTION 37 Consider the following work breakdown structure: Activity Start Node 1 1 2 2 3 4 5 Finish Node 2 3 4

84 093 QUESTION 37 Consider the following work

84 093 QUESTION 37 Consider the following work breakdown structure: Activity Start Node 1 1 2 2 3 4 5 Finish Node 2 3 4 5 5 Duration Estimate (Days) Optimistic Most Likely Pessimistic 9 15 21 13 21 23 6 9 18 23 35 47 19 26 27 23 29 41 14 20 26 2 8 G H 6 7 What is the critical path for this project network? O A-B-C-D-E-F-G O A-C-F-H A-D-G-H OB-E-G-H ch EN (hp