Question: Consider the following work breakdown structure: activity Start node Finish Node Optimistic Most likely Pessimistic A 1 2 9 15 21 B 1 3 13
Consider the following work breakdown structure:
| activity | Start node | Finish Node | Optimistic | Most likely | Pessimistic |
| A | 1 | 2 | 9 | 15 | 21 |
| B | 1 | 3 | 13 | 21 | 23 |
| C | 2 | 4 | 6 | 9 | 18 |
| D | 2 | 5 | 23 | 35 | 47 |
| E | 3 | 5 | 19 | 26 | 27 |
| F | 4 | 6 | 23 | 29 | 41 |
| G | 5 | 6 | 14 | 20 | 26 |
| H | 6 | 7 | 2 | 5 | 8 |
What are the estimated slack times (in weeks) for activities A-H?
| 1; 5; 0; 3; 10; 0; 0; 3; 2 | ||
| 10; 0; 1; 5; 0; 5; 0; 10 | ||
| 5; 1; 5; 0; 15; 5; 3; 0 | ||
| 0; 5; 15; 0; 5; 15; 0; 0 |