Question: Consider the following work breakdown structure: activity Start node Finish Node Optimistic Most likely Pessimistic A 1 2 9 15 21 B 1 3 13

Consider the following work breakdown structure:

activity

Start

node

Finish

Node

Optimistic Most likely Pessimistic
A 1 2 9 15 21
B 1 3 13 21 23
C 2 4 6 9 18
D 2 5 23 35 47
E 3 5 19 26 27
F 4 6 23 29 41
G 5 6 14 20 26
H 6 7 2 5 8

What are the estimated slack times (in weeks) for activities A-H?

1; 5; 0; 3; 10; 0; 0; 3; 2

10; 0; 1; 5; 0; 5; 0; 10

5; 1; 5; 0; 15; 5; 3; 0

0; 5; 15; 0; 5; 15; 0; 0