Question: Consider the following work breakdown structure: Start Finish Time Estimates(wks) Activity Node Node t o t m t p A 1 2 11 20 29
Consider the following work breakdown structure:
| Start | Finish | Time Estimates(wks) | ||||||||||
| Activity | Node | Node | to | tm | tp | |||||||
| A | 1 | 2 | 11 | 20 | 29 | |||||||
| B | 2 | 3 | 2 | 5 | 8 | |||||||
| C | 2 | 4 | 18 | 30 | 42 | |||||||
| D | 3 | 4 | 7 | 10 | 13 | |||||||
| E | 1 | 4 | 31 | 40 | 43 | |||||||
What is the estimated slack time for activity E?
Multiple Choice
-
0 weeks
-
3 weeks
-
9 weeks
-
11 weeksCorrect
-
12 weeks