Question: Consider the following work breakdown structure: table [ [ , Start,Finish, table [ [ Duration ( days ) ] , [ Activity ]

Consider the following work breakdown structure:
\table[[,Start,Finish,\table[[Duration (days)],[Activity]],Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59,,,,,,,],[B,1,3,54,60,66,,,,,,,],[C,2,4,58,70,82,,,,,,,],[D,3,4,32,41,44,,,,,,,]]
What is the estimated standard deviation in the time for activity D?
 Consider the following work breakdown structure: \table[[,Start,Finish,\table[[Duration (days)],[Activity]],Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59,,,,,,,],[B,1,3,54,60,66,,,,,,,],[C,2,4,58,70,82,,,,,,,],[D,3,4,32,41,44,,,,,,,]] What is