Consider the following work breakdown structure:
\table[[Activity,Precedes,\table[[Duration Estimates (Days)],[Optimistic]],Most Likely,Pessimistic],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W,X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]]
What is the estimated expected (mean) time for project completion?
135 days
145 days
170 days
180 days
255 days
 Consider the following work breakdown structure: \table[[Activity,Precedes,\table[[Duration Estimates (Days)],[Optimistic]],Most Likely,Pessimistic],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W,X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]] What

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!