Question: Consider the following work breakdown structure: Activity Start Node Finish Node Duration ( days ) Optimistic Most Likely Pessimistic A 1 2 4 1 5
Consider the following work breakdown structure:
Activity Start Node Finish Node Duration days
Optimistic Most Likely Pessimistic
A
B
C
D
What is the estimated expected mean time for activity D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
