Question: Consider the following work breakdown structure: 12 Activity A B Start Node 1 1 2 3 Finish Node 2 3 Duration (days) Most Likely 50

Consider the following work breakdown structure:
Consider the following work breakdown structure:
Consider the following work breakdown structure: 12 Activity A B Start Node 1 1 2 3 Finish Node 2 3 Duration (days) Most Likely 50 60 70 41 Optimistic 41 54 58 32 8 022112 Pessimistic 59 66 82 44 4 D References What is the estimated expected (mean) time for activity D? 12 O 41 days 8 02 20:54 42 days References 32 days 44 days 40 days