Question: Consider the following work breakdown structure: table [ [ , , , Time Estimates ( days ) , ] , [ Activity , Precedes,Optimistic,Most

Consider the following work breakdown structure:
\table[[,,,Time Estimates (days),],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B, C,-,-,62],[A,D,38,50,108],[B,E,90,99,115],[C,End,85,100,31],[D,F,19,25,115],[E,End,91,100,68]]
What is the estimated expected (mean) time for project completion?A.199days b.100days c.140days d.440days e.200days
 Consider the following work breakdown structure: \table[[,,,Time Estimates (days),],[Activity,Precedes,Optimistic,Most Likely,Pessimistic],[Start,A, B,