Question: Consider the following work breakdown structure: table [ [ , Start,Finish,Duration Estimate ( Days ) , ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ]

Consider the following work breakdown structure:
\table[[,Start,Finish,Duration Estimate (Days),],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,9,15,21],[B,1,3,13,21,23],[C,2,4,6,9,18],[D,2,5,23,35,47],[E,3,5,19,26,27],[F,4,6,23,29,41],[G,5,6,14,20,26],[H,6,7,2,5,8]]
What is the probability that the critical path for this project will be completed within 75 weeks? (Please use decimal point format.)
Within what amount of time in weeks is there a 90% probability that the critical path for this project will be completed ?