Question: Consider the following work breakdown structure: table [ [ , Start,Finish,Duration Estimate ( Days ) , ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ]
Consider the following work breakdown structure:
tableStart,Finish,Duration Estimate DaysActivityNode,Node,Optimistic,Most Likely,PessimisticABCDEFGH
What is the probability that the critical path for this project will be completed within weeks? Please use decimal point format.
Within what amount of time in weeks is there a probability that the critical path for this project will be completed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
