Question: Consider the following work breakdown structure: table [ [ , table [ [ Start ] , [ Activity ] , [ Node ]

Consider the following work breakdown structure:
\table[[,\table[[Start],[Activity],[Node]],\table[[Finish],[Node]],\table[[Duration (days)],[Optimistic]],Most Likely,Pessimistic],[A,1,2,41,50,59,,,],[B,1,3,54,60,66,,,],[C,2,4,58,70,82,,,],[D,3,4,32,41,44,,,]]
What is the probability that this project will be completed within 130 days?
 Consider the following work breakdown structure: \table[[,\table[[Start],[Activity],[Node]],\table[[Finish],[Node]],\table[[Duration (days)],[Optimistic]],Most Likely,Pessimistic],[A,1,2,41,50,59,,,],[B,1,3,54,60,66,,,],[C,2,4,58,70,82,,,],[D,3,4,32,41,44,,,]] What is