Question: Consider the following work breakdown structure: Time Estimates ( days ) Activity Precedes Optimistic Most Likely Pessimistic Start A , B - - - A

Consider the following work breakdown structure:
Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A,B ---
A C,D 445056
B D 456075
C E 424548
D F 314049
E F 273639
F End 587082
What is the estimated expected (mean) time for activity E?