Question: Consider the following work breakdown structure: Time Estimates ( days ) Activity Precedes Optimistic Most Likely Pessimistic Start A , B - - - A
Consider the following work breakdown structure:
Time Estimates days
Activity Precedes Optimistic Most Likely Pessimistic
Start AB
A CD
B D
C E
D F
E F
F End
What is the estimated expected mean time for activity E
Multiple Choice
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
