Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic - Activity Start A B D Precedes A,B C,D D E F

Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic - Activity Start A B D Precedes A,B C,D D E F F End 44 45 42 50 60 45 40 31 56 75 48 49 39 82 E F 36 27 58 70 What is the estimated slack time for activity D