Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B CD D B 44 45 42 31

Consider the following work breakdown structure:
Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start A Precedes A,B CD D B 44 45 42 31 27 58 50 60 45 40 36 70 56 75 48 49 39 82 D F F End What is the estimated expected (mean) time for project completion? Multiple Choice 210 days 200 days 170 days 300 days 160 days