Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start 44 Precedes A,B C,D D E F B 45 C

Consider the following work breakdown structure:Consider the following work breakdown structure:

Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start 44 Precedes A,B C,D D E F B 45 C 50 60 45 40 36 70 42 31 27 56 75 48 49 39 82 D F E F End 58 What is the estimated expected (mean) time for project completion? Multiple Choice O 160 days 170 days 200 days 210 days 300 days