Question: Consider the following work breakdown structure for a project: Activity Start Node A 1 Finish Node Optimistic Time 2 31 Most Likely Time Pessimistic Time

Consider the following work breakdown structure

Consider the following work breakdown structure for a project: Activity Start Node A 1 Finish Node Optimistic Time 2 31 Most Likely Time Pessimistic Time 40 49 50 56 60 172 B 1 3 44 C 2 4 48 42 D 3 4 31 34 What is the probability that this project will be completed within 120 days