Question: Consider the following work breakdown structure: What is the estimated expected (mean) time for activity E? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic

Consider the following work breakdown structure: What is the estimated expected (mean) time for activity E?

Time Estimates (days)

Activity

Precedes

Optimistic

Most Likely

Pessimistic

Start

A,B

-

-

-

A

C,D

44

50

56

B

D

45

60

75

C

E

42

45

48

D

F

31

40

49

E

F

27

36

39

F

End

58

70

82

53.

35.

39.

36.

25.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!