Question: Question 2. Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total Float(slack) for the activities. Also

Question 2. Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total Float(slack) for the activities. Also draw the Network Diagram for the given schedule and show critical path on it. Calculate the deadline for finishing the above project with an 80% likelihood, assume Z=1.04 if the variance along the critical path= 0.1 Project Duration (critical time of the project)