Question: Question 3 Consider the network described in the table below. Activity Preceding Optimistic Probable Pessimistic A 5 11 14 B 3 3 9 Ic 6

Question 3 Consider the network described in the
Question 3 Consider the network described in the table below. Activity Preceding Optimistic Probable Pessimistic A 5 11 14 B 3 3 9 Ic 6 10 14 D AB 3 5 7 E B 4 6 11 F 6 8 13 G DE 2 4 6 H F 3 3 9 Calculate the Variance of the project 0 1.78 O 1.36 04.14 0 5.82 O None of the above