Question: Consider the network described in the table below. Times are given in weeks (keep two decimal places). Activity Immediate Predecessor(s) Pessimistic b Most Likely m
Consider the network described in the table below. Times are given in weeks (keep two decimal places). Activity Immediate Predecessor(s) Pessimistic b Most Likely m Optimistic a A -- 15 10 8 B -- 9 8 7 C A,B 10 6 5 D B,C 3 3 3 E D 9 5 1 F C,E 11 8 5 c. Find the critical path of the project and its duration (using the longest path duration method). solve using excel