Question: Consider the network described in the table below. Times are given in weeks (keep two decimal places). Activity Immediate Predecessor(s) Pessimistic b Most Likely m
Consider the network described in the table below. Times are given in weeks (keep two decimal places).
| Activity | Immediate Predecessor(s) | Pessimistic b | Most Likely m | Optimistic a |
| A | -- | 15 | 10 | 8 |
| B | -- | 9 | 8 | 7 |
| C | A,B | 10 | 6 | 5 |
| D | B,C | 3 | 3 | 3 |
| E | D | 9 | 5 | 1 |
| F | C,E | 11 | 8 | 5 |
- Draw the network diagram.
- Calculate the expected time and variance of each activity.
- Find the critical path of the project and its duration.
- Calculate the probability that the project will be completed in more than 35 weeks.