Question: Consider the project activity information below. The indirect cost for this project is $88 per day. All activities can be partially crashed (i.e. shortened by

Consider the project activity information below. The indirect cost for this project is $88 per day. All activities can be partially crashed (i.e. shortened by 1 day at a time).

Activity Predecessor Normal Duration (days) Crashed Duration (days) Normal Cost ($) Crashed Cost ($)
A - 9 8 900 940
B - 6 5 900 920
C A 5 1 1000 1240
D A 10 8 700 800
E B 11 2 900 1710
F D,E 3 1 500 660

All activities are connected through FS relationships with no lead or lag. First, please determine the normal project duration and the normal cost. The normal project duration is days. The normal project cost is $ (Round to the nearest full dollar. Remember: Never enter dollar signs!) You are now asked to crash the project by 3 days. Make sure you show each crashing step in detail in your solutions file, which you're required to upload as well.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!