Question: Consider the project activity information below. The indirect cost for this project is $88 per day. All activities can be partially crashed (i.e. shortened by
Consider the project activity information below. The indirect cost for this project is $88 per day. All activities can be partially crashed (i.e. shortened by 1 day at a time).
| Activity | Predecessor | Normal Duration (days) | Crashed Duration (days) | Normal Cost ($) | Crashed Cost ($) |
| A | - | 9 | 8 | 900 | 940 |
| B | - | 6 | 5 | 900 | 920 |
| C | A | 5 | 1 | 1000 | 1240 |
| D | A | 10 | 8 | 700 | 800 |
| E | B | 11 | 2 | 900 | 1710 |
| F | D,E | 3 | 1 | 500 | 660 |
All activities are connected through FS relationships with no lead or lag. First, please determine the normal project duration and the normal cost. The normal project duration is days. The normal project cost is $ (Round to the nearest full dollar. Remember: Never enter dollar signs!) You are now asked to crash the project by 3 days. Make sure you show each crashing step in detail in your solutions file, which you're required to upload as well.