Question: Consider the project as outlined in the tables below: A . Crash the project to its minimum: What is the minimum crashing time? B .

Consider the project as outlined in the tables below:
A. Crash the project to its minimum: What is the minimum crashing time?
B.What is the total crashing cost?
C.Assuming that the indirect cost is $8000,What is the total project after crashing? NOTE: Total project cost after crashing= Project duration(after crashing)x indirect cost+sigma/sum of[each activity time(after crashing)x its normal cost/week]+total crashing cost.
 Consider the project as outlined in the tables below: A. Crash

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!