Question: Consider the project information in the table below ( time in days ) . Find the following: 1 . constructs the CPM network diagram for

Consider the project information in the table below (time in days). Find the following: 1. constructs the CPM network diagram for this project; 2. compute the forward and backward pass); and 3. find the critical path (compute and show the slack time each activity).
\table[[ACTIVITY,\table[[IMMEDIATE],[PREDECESSORS]],Time],[A,-,23],[B,-,20],[C,A,B,12],[D,B,C,19],[E,A,17],[F,C,D,E,24]]
 Consider the project information in the table below (time in days).