Question: Consider the project information in the table below: Activities Duration (days) Immediate Predecessors A 8 B 00 000 9 8 B 00 D 11 A

Consider the project information in the table
Consider the project information in the table below: Activities Duration (days) Immediate Predecessors A 8 B 00 000 9 8 B 00 D 11 A m E 6 A F 6 B G 5 C H 4 C 1 5 F, G, H J 2 D, E, Draw and analyze a project network diagram to answer the following questions: What is the most that Activity E can be delayed in starting, without delaying the project? A. 22 B. 21 C. 19 D. 20 E. 18