Question: Consider the project network and data shown below. Determine the critical path of this project network. C (7) D (6) F (3) A (7) |

Consider the project network and data shown

Consider the project network and data shown below. Determine the critical path of this project network. C (7) D (6) F (3) A (7) | G (3) | (6) B (12) E (8) H (4) Select one: O a. A-B-E-H-| O b. A-C-D-F- O c. A-C-D-G-| O d. A-C-D-E-H-|