Question: PROBLEM # 4 Consider the project network and data shown below: Answer in the Blue Sheet Below ( You must show all formulas, calculations, and
PROBLEM # Consider the project network and data shown below:
Answer in the Blue Sheet Below
You must show all formulas, calculations, and "highlight" corrrect Answers
A Determine the critical path and the project completion time. Normal Crash Normal Crash Crash Cost
B Determine the crash cost per week for all activities. Complete the Chart at the Right Activity Slack Time Time Cost Cost Per Week
A $ $
B $ $
C $ $
D $ $
E $ $
F $ $
G $ $
H $ $
I $ $
C Which activities need to be crashed to reduce the project's completion time by weeks? How much does this cost?