Question: PROBLEM # 4 Consider the project network and data shown below: Answer in the Blue Sheet Below ( You must show all formulas, calculations, and

PROBLEM #4 Consider the project network and data shown below:
Answer in the Blue Sheet Below
(You must show all formulas, calculations, and "highlight" corrrect Answers)
A. Determine the critical path and the project completion time. Normal Crash Normal Crash Crash Cost
B. Determine the crash cost per week for all activities. Complete the Chart at the Right Activity Slack Time Time Cost Cost Per Week
A 074 $400 $750
B 1129 $1,000 $2,200
C 076 $800 $1,100
D 065 $600 $1,000
E 086 $1,200 $2,200
F 932 $800 $1,000
G 932 $500 $650
H 043 $400 $600
I 065 $900 $1,300
C. Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!