Question: Consider the project where the duration is in days. Activity 1 2 3 Duration 3 2 3 Predecessors 2.7 | 31 --- 4 1 3

Consider the project where the duration is in

Consider the project where the duration is in days. Activity 1 2 3 Duration 3 2 3 Predecessors 2.7 | 31 --- 4 1 3 5 3 1,6 6 2 4, 7 7 3 1 3 Question 2. What is the time of completion? (A) 9 (B) 6 (C) 12 (D) 17 (E) none of the above Question 3. Which activity has the latest early finish? (A) 6 (B) 7 (C) 4 (D) 5 (E) none of the above Question 4. What is the critical path? (A) 1,3,5,7 (B) 1,2,3,5 (C) 3,4,5,6 (D) 3,5,6,7 (E) 1,2,3,7