Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the project with the following dependency matrix.
Activity | Predecessor | Activity Times (Days) |
1 | 2 | |
2 | 1 | 5 |
3 | 2 | 7 |
4 | 2 | 3 |
5 | 2 | 4 |
6 | 4,5 | 6 |
7 | 3,6 | 3 |
8 | 6,7 | 8 |
a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.
b) Draw a Gantt chart for this project including slack times (Optional: utilize commercial software if possible).