Question: Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1 5 3 2 7 4 2 3 5
Consider the project with the following dependency matrix.
| Activity | Predecessor | Activity Times (Days) |
| 1 | 2 | |
| 2 | 1 | 5 |
| 3 | 2 | 7 |
| 4 | 2 | 3 |
| 5 | 2 | 4 |
| 6 | 4,5 | 6 |
| 7 | 3,6 | 3 |
| 8 | 6,7 | 8 |
a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.
b) Draw a Gantt chart for this project including slack times (Optional: utilize commercial software if possible).
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
Lets start with part a drawing the ... View full answer