Question: Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1 5 3 2 7 4 2 3 5

Consider the project with the following dependency matrix.

ActivityPredecessorActivity Times (Days)
12
215
327
423
524
64,56
73,63
86,78

a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.