Question: Consider the two different project types below. For each project type, consider which areas of the Cost Management Plan would be most important, and explain
Consider the two different project types below. For each project type, consider which areas of the Cost Management Plan would be most important, and explain your rationale for each in the space provided:
Cost Management Plan Components:
Project: Purchasing a PC for college
| Units of Measure | |
| Level Of Precision | |
| Level Of Accuracy | |
| Organizational Procedure Links | |
| Control Thresholds | |
| Rules of Performance Measurement | |
| Reporting Formats | |
| Additional Details |
Step by Step Solution
There are 3 Steps involved in it
Project Purchasing a PC for college 1 Units of Measure In this project the units of measure would be important to determine the quantity and specifica... View full answer