Question: Consider the Work Breakdown Structure of this project... Immediate Predecessor(s) Activity A B C D E F G none A A B C, D

Consider the Work Breakdown Structure of this project... Immediate Predecessor(s) Activity A 

Consider the Work Breakdown Structure of this project... Immediate Predecessor(s) Activity A B C D E F G none A A B C, D C, D E, F At a minimum, how long will this project take (in days)? Duration (days) 8 10 8 13 5 7 9

Step by Step Solution

3.41 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Lets analyze the given information and calculate the critical path Activity A has a duration of 8 da... View full answer