Question: Consider the Work Breakdown Structure of this project Immediate Duration Activity Predecessor(s) (days) A none 6 B A 14 A 10 D B 9 E

Consider the Work Breakdown Structure of this

Consider the Work Breakdown Structure of this project Immediate Duration Activity Predecessor(s) (days) A none 6 B A 14 A 10 D B 9 E C, D 11 F C, D 14 G E, F 9 At a minimum, how long will this project take (in days)