Question: ID Slope Normal Time Normal Cost, $ Crash Time Crash Cost, $ A 25 8 150 6 200 B 150 4 200 3 350 C

ID Slope Normal Time Normal Cost, $ Crash Time Crash Cost, $
A 25 8 150 6 200
B 150 4 200 3 350
C 100 8 150 7 250
D 100 7 350 4 650
E 75 9 250 7 400
F 150 7 500 6 650
G 200 4 400 3 600
H 50 8 400 6 500
I 175 7 100 5 450

Given the above table of Software Developing Project, what is the total normal cost of the project?

Answer:

Consider your calculations from the previous question.

If the critical path is B-D-E-H-I, which activity should be crashed first.

Select one:

Activity A

Activity B

Activity C

Activity D

Activity E

Activity F

Activity G

Activity H

Activity I

Flag question

Question text

If you were asked to reduce the project by three days, what activities would you crash?

* Iteration 1: Activity AnswerABCDEFGHI

* Iteration 2: Activity AnswerABCDEFGHI

* Iteration 3: Activity AnswerABCDEFGHI

Question text

What is the extra amount you will have to pay for crashing the project by three days?

Answer:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!