Question: Considering the below information about a software engineering project, what is the Cost Variance? Planned Value (PV) = 6,000 Earned Value (EV) = 4,000 Actual

Considering the below information about a software engineering project, what is the Cost Variance?

Planned Value (PV) = 6,000

Earned Value (EV) = 4,000

Actual Cost (AC) = 6,000

Project term: 24 months

-4,000

4,000

-2,000

0