Question: Considering the below information about a software engineering project, what is the Cost Variance? Planned Value (PV) = 6,000 Earned Value (EV) = 4,000 Actual
Considering the below information about a software engineering project, what is the Cost Variance?
Planned Value (PV) = 6,000
Earned Value (EV) = 4,000
Actual Cost (AC) = 6,000
Project term: 24 months
| -4,000 | ||
| 4,000 | ||
| -2,000 | ||
| 0 |