Question: Considering the below information about a software engineering project, what is the Cost Variance? Planned Value (PV) = 8,000 Earned Value (EV) = 12,000 Actual
Considering the below information about a software engineering project, what is the Cost Variance?
Planned Value (PV) = 8,000
Earned Value (EV) = 12,000
Actual Cost (AC) = 6,000
Project term: 12 months
1) 8,000
2) 6,000
3) 4,000
4) None of the above