Question: Construct a Gantt chart with the following * Total duration(weeks), Critical and Non Critical Tasks, Total Slack and the project end date if the start

Construct a Gantt chart with the following
* Total duration(weeks), Critical and Non Critical Tasks, Total Slack and the project end date if the start date is 5/11/20
Task ID Description Immediate Predecessor Estimated Duration (Weeks) Foundation and Framing - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - A Foundation B Construct Rough wall C Install Roof/Doors/Windows - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Interior Works D Install Electrical Wiring E Set up Wallboard CD F Paint Interior Walls G Install Flooring Install Interior Fixtures - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Exterior Works . - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Paint Exterior Walls and Install Exterior Fixtures J Construct Driveway and Walkway HIStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts