Question: 1. Construct a PERT/CPM network for a project that has the following activities; Activities Labor Lead Activities Duration/ Weeks A B E F G H

1. Construct a PERT/CPM network for a project

1. Construct a PERT/CPM network for a project that has the following activities; Activities Labor Lead Activities Duration/ Weeks A B E F G H 1 A A B B DE F 3 3 4 2 4 2 3 2 3 9 7 8 6 9 10 9 12 9 a. How long will it take to complete this project? b. Identify the critical path and their slack for each activity. c. Compare the weekly labor usage with Earlier Start (ES), earlier Finish (EF) and Last Start (LS), Last Finish (LF) approach