Question: Construct a precedence diagram from the information presented in Table 1 . Provide a legend indicating: task, duration, earliest start, earliest finish, latest start, latest

Construct a precedence diagram from the information presented in Table 1. Provide a legend indicating: task, duration, earliest start, earliest finish, latest start, latest finish, and slack.
Table 1
Task Predecessor Duration (days) A None 3 BA4 CA2 DB5 EC1 FC2
G D,E 4 H F,G 3