Question: Construct on a NETWORK DIAGRAM ONLY schedule using the critical path method ( activity on the node ) . Complete a forward and backward pass
Construct on a NETWORK DIAGRAM ONLY schedule using the critical path method activity on the node Complete a forward and backward pass to calculate start and finish dates, float, and the critical path. Your schedule should show:
Tasks on nodes
Task early start and finish, late start and finish, and float
Project critical path
All work MUST BE DONE ON NETWORK DIAGRAM TO SHOWtableTaskPredecessor,DurationABACADCEBFBGEHFID
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
