Question: Construct on a NETWORK DIAGRAM ONLY schedule using the critical path method ( activity on the node ) . Complete a forward and backward pass

Construct on a NETWORK DIAGRAM ONLY schedule using the critical path method (activity on the node). Complete a forward and backward pass to calculate start and finish dates, float, and the critical path. Your schedule should show:
Tasks on nodes
Task early start and finish, late start and finish, and float
Project critical path
All work MUST BE DONE ON NETWORK DIAGRAM TO SHOW\table[[Task,Predecessor,Duration],[A,,9],[B,A,16],[C,A,10],[D,C,6],[E,B,12],[F,B,12],[G,E,10],[H,F,7],[I,D,3]]
 Construct on a NETWORK DIAGRAM ONLY schedule using the critical path

Step by Step Solution