Question: Construct the AON and AOA network based on the activity descriptions below. Activities A, B, and C start the project. Activity D can start when
Construct the AON and AOA network based on the activity descriptions below.
Activities A, B, and C start the project.
Activity D can start when Activities A and B are completed.
Activity E also depends on Activity B.
Activity F follows Activity C and precedes Activity G.
Activity G is also preceded by Activities D and E.