Question: correct answer is shown, need explanation on how to arrive at answer. Consider the following work breakdown structure: What is the probability that the critical
correct answer is shown, need explanation on how to arrive at answer.
Consider the following work breakdown structure: What is the probability that the critical path for this project will be completed within 210 days? Multiple Choice .9772
Step by Step Solution
There are 3 Steps involved in it