A project's activities must be completed in the sequence indicated below. Duration in Weeks Activity Immediately preceding Activity 3 A 20 B 15 10 D 5 E 4 A F 3 D G 10 D, E H 3 F 10 B J 7 G H K 5 BI L The project ends with the intersection of activities: C, J, K and L Use CPM to construct (Draw) the project Network and find the critical path. How long is the project expected to take