Question: A project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Activity Duration in Weeks A - 3 B - 20 C
A project's activities must be completed in the sequence indicated below.
| Activity | Immediately Preceding Activity | Duration in Weeks |
| A | - | 3 |
| B | - | 20 |
| C | - | 15 |
| D | - | 10 |
| E | - | 5 |
| F | A | 4 |
| G | D | 3 |
| H | D, E | 10 |
| I | F | 3 |
| J | B | 10 |
| K | G, H | 7 |
| L | B, I | 5 |
| The project ends with the intersection of activities: C, J, K and L | ||
1- Use CPM to construct (Draw) the project Network and find the critical path.
2- How long is the project expected to take?