Question: CPM Exercise Task Optimistic Realistic Pessimistic ETD Preceding Task(s) 1 1 5 9 - 2 3 4 5 1 3 3 6 9 1 4
CPM Exercise
| Task | Optimistic | Realistic | Pessimistic | ETD | Preceding Task(s) |
| 1 | 1 | 5 | 9 |
| - |
| 2 | 3 | 4 | 5 |
| 1 |
| 3 | 3 | 6 | 9 |
| 1 |
| 4 | 1 | 2 | 3 |
| 2, 3 |
| 5 | 2 | 6 | 8 |
| 4 |
| 6 | 4 | 5 | 6 |
| 4 |
| 7 | 1 | 3 | 5 |
| 6 |
| 8 | 1 | 2 | 3 |
| 5, 7 |
Complete the WBS above. Using a network diagram and CPM answer the following :
- the earliest finish time for this project?
- which tasks are on the critical path?
- which tasks have slack, how much slack do they have?