Question: CPM Exercise Task Optimistic Realistic Pessimistic ETD Preceding Task(s) 1 1 5 9 - 2 3 4 5 1 3 3 6 9 1 4

CPM Exercise

Task

Optimistic

Realistic

Pessimistic

ETD

Preceding Task(s)

1

1

5

9

-

2

3

4

5

1

3

3

6

9

1

4

1

2

3

2, 3

5

2

6

8

4

6

4

5

6

4

7

1

3

5

6

8

1

2

3

5, 7

Complete the WBS above. Using a network diagram and CPM answer the following :

  1. the earliest finish time for this project?
  2. which tasks are on the critical path?
  3. which tasks have slack, how much slack do they have?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!