Question: CPM PERT CHART 1. Calculate the expected project time? 2. Draw PERT Chart? 3. Count the following: Early Start (ES) Early Finish (EF) Lately Start
CPM PERT CHART
1. Calculate the expected project time?
2. Draw PERT Chart?
3. Count the following:
- Early Start (ES)
- Early Finish (EF)
- Lately Start (LS)
- Lately Finish (LF)
- Slack
4. Calculating the redundant times of activities and determining the critical path.
| Activity | Predecessor activity | Optimistic time (a) | Likely time (m) | Pessimistic time (b) | Expected Time T =(a+4m+b)/6 |
| A | ---- | 1 | 2 | 4 |
|
| B | ---- | 3 | 3.5 | 4 |
|
| C | ---- | 10 | 12 | 13 |
|
| D | ---- | 4 | 5 | 7 |
|
| E | ---- | 2 | 4 | 5 |
|
| F | A | 6 | 7 | 8 |
|
| G | B | 2 | 4 | 5.5 |
|
| H | C | 5 | 7.7 | 9 |
|
| I | C | 9.9 | 10 | 12 |
|
| J | C | 2 | 4 | 5 |
|
| K | D | 2 | 4 | 6 |
|
| L | E | 2 | 4 | 6 |
|
| M | F,G,H | 5 | 6 | 6.5 |
|
| N | J,K,L | 1 | 1.1 | 2 |
|
| O | I,M | 5 | 7 | 8 |
|
| P | N | 5 | 7 | 9 |
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
