Question: CPM PERT CHART 1. Calculate the expected project time? 2. Draw PERT Chart? 3. Count the following: Early Start (ES) Early Finish (EF) Lately Start

CPM PERT CHART

1. Calculate the expected project time?

2. Draw PERT Chart?

3. Count the following:

  1. Early Start (ES)
  2. Early Finish (EF)
  3. Lately Start (LS)
  4. Lately Finish (LF)
  5. Slack

4. Calculating the redundant times of activities and determining the critical path.

Activity

Predecessor activity

Optimistic time

(a)

Likely time

(m)

Pessimistic time

(b)

Expected Time

T =(a+4m+b)/6

A

----

1

2

4

B

----

3

3.5

4

C

----

10

12

13

D

----

4

5

7

E

----

2

4

5

F

A

6

7

8

G

B

2

4

5.5

H

C

5

7.7

9

I

C

9.9

10

12

J

C

2

4

5

K

D

2

4

6

L

E

2

4

6

M

F,G,H

5

6

6.5

N

J,K,L

1

1.1

2

O

I,M

5

7

8

P

N

5

7

9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!